Risk, legal & society · Risk

Risk register

Best for Startup to Enterprise

RISKOWNERLIKELIHOODIMPACTCONTROLSTREATMENTSTATUS

Use it when

You have identified risks across a project, unit or company and need one record of their ratings, owners, responses and status that stays current.

Skip it when

  • You need to show leaders where scored risks cluster. Use Risk heat map on the finished register.
  • You still need to set risk criteria, appetite and the wider risk process. Use ISO 31000 risk management or COSO enterprise risk management first, and keep the register as its record.

What to apply first and what to use instead are listed below.

Inputs

  • Identified risks
    Risks from workshops, assessments or incident reviews, each with a known cause and effect.
  • Rating scales
    The likelihood and impact scales and the rule that combines them into an exposure rating, from your risk policy.
  • Category list
    A fixed set of risk categories, such as strategic, operational and financial, so registers can be combined later.
  • Owners
    A named person accountable for each risk, agreed with their manager.
  • Response options
    The agreed response types (accept, mitigate, transfer or avoid) and the tolerance above which acceptance needs approval.

Steps

  1. Set up the columns, covering ID, category, description, likelihood, impact, exposure rating, priority, response type, response description and cost, owner and status.
  2. Enter each risk with an ID and a category, and write its description as cause, event and effect.
  3. Rate likelihood and impact on the agreed scales, combine them into an exposure rating, and rank the risks into a priority order.
  4. Assign an owner and a response type to each risk, then describe the response and estimate its cost.
  5. Set each risk's status, such as proposed, active or retired, and log every change in a notes column with the date.
  6. Review the register on a fixed cycle and after major changes, update ratings once responses take effect, and pass the top risks to the enterprise risk list.

Output

A single dated risk register with one row per risk, ranked by priority, ready for owners to update and for roll-up into an enterprise risk profile.

  • ID and category
  • Description (cause, event, effect)
  • Likelihood and impact
  • Exposure rating and priority
  • Response type and description
  • Response cost
  • Owner
  • Status and last review date

Done when

  • Every row has an ID, category, description, rating, owner, response and status.
  • Every description names a cause, an event and an effect.
  • All ratings use the same scales.
  • Rows are sorted by priority and the register shows its last review date.
  • Every risk rated above tolerance has a mitigate, transfer or avoid response with a cost estimate, or an approved acceptance.

Measure

At each review cycle, track how many risks sit above tolerance, how many responses are overdue, and how many incidents came from risks missing from the register. Compare with your own previous three cycles. It is working when overdue responses fall and nearly every incident traces back to a risk that was already recorded and owned.

Hypothetical example

Larkspur Clinics, with three sites, built a register for its move to a new patient records system. The team logged 18 risks on a five-point scale. One read "Staff untrained on the new system (cause) enter allergies in the wrong field (event), so clinicians miss them (effect)." It was rated likely and severe, the top priority. The clinical lead took ownership, chose to mitigate with supervised data entry for the first month, and costed it at 12,000 dollars. A risk of a short outage during cutover was accepted because it fell within tolerance. The register was reviewed every two weeks, and the top three risks went to the board's risk list.

Common mistakes

  • Writing vague risks such as "IT failure". Write the cause, event and effect so the owner knows what to act on.
  • Filling the register once and filing it. Review it on a fixed cycle and after major changes, and update ratings as responses take effect.
  • Keeping a register that no decision uses. Link the top risks to the decisions they affect and pass them up to the enterprise list.

Sources

Show all 4 sources

By company stage

  1. Pre-IdeaNot applicableThere is nothing to register without a product or venture.
  2. IdeaUsefulA short list of key risks helps but formal ownership is premature.
  3. Early StartupUsefulA simple list of top risks is helpful for investors and focus without needing full process.
  4. StartupCriticalTeam leads need named owners and responses for risks as the company scales.
  5. GrowthCriticalDepartments and investors expect an auditable record of risk ratings, owners and responses.
  6. ScaleCriticalMultiple products and regulators require a current, consistent register across units.
  7. EnterpriseCriticalEnterprise governance and audit rely on registers as the core record of risk.

Apply first

Nothing. You can start here.

Use instead

  • Risk heat map

    You need to show leaders where scored risks cluster. Use Risk heat map on the finished register.

  • COSO enterprise risk management

    You still need to set risk criteria, appetite and the wider risk process. Use ISO 31000 risk management or COSO enterprise risk management first, and keep the register as its record.

  • ISO 31000 risk management

    You still need to set risk criteria, appetite and the wider risk process. Use ISO 31000 risk management or COSO enterprise risk management first, and keep the register as its record.

Recommended resources

No sponsored resources on this framework yet. Sponsored listings would be labelled here, never in search.

Progress is not saved until you have an account. Create a free account