Critical path method (CPM)

1FORWARD PASS2BACKWARD PA…3FLOAT4CRITICAL PA…

Use it when

Your project has a fixed scope with known task dependencies, and you need its earliest finish date and the chain of activities that controls that date.

Skip it when

  • Scope will change as you learn, and you plan in short iterations. Use Agile release planning instead.
  • The schedule asks for more people or equipment than you have in some weeks. Build the network here first, then use Resource optimization framework to level it.
  • Shared people juggle several tasks and padded estimates still finish late. Use Critical chain project management (CCPM), which starts from this network and adds buffers.
  • One machine or work center limits what a plant ships. Use Drum-buffer-rope (Goldratt).

What to apply first and what to use instead are listed below.

Inputs

  • Work breakdown structure
    The deliverables broken into work packages, from the project charter and scope statement.
  • Activity list
    Every activity needed to deliver the scope, each with a verb-led name and one responsible person, from the team that will do the work.
  • Dependencies
    Predecessors and successors for each activity with the relationship type, mostly finish-to-start, and any lag that stands for real waiting time.
  • Duration estimates
    Working days for each activity with the resources assumed, from the activity owners and records of similar past work.
  • Calendars and fixed dates
    Working days, holidays and any contract dates that cannot move.
  • Resource availabilityOptional
    People and equipment available per week, needed when they could change the dates.

Steps

  1. List the start and finish milestones and every activity from the work breakdown structure, each with one owner and a duration shorter than about two update cycles.
  2. Link every activity to at least one predecessor and one successor, using finish-to-start wherever possible, so only the start and finish milestones have open ends.
  3. Run the forward pass from the start date to get each activity's early start and early finish, and the earliest project finish.
  4. Run the backward pass from the finish date to get late start and late finish, then calculate total float and free float for every activity.
  5. Mark the critical path as the longest path, with the lowest total float, and list near-critical activities inside a float threshold you set for this project. Trace any very high or negative float to missing logic or a date constraint.
  6. If the finish is too late, crash or fast-track critical activities and rerun the passes. Get the team's approval, save the baseline and update it at each status date with actual dates and remaining durations.

Output

A baselined network schedule with the critical path highlighted and a float table for every activity.

  • Activity and owner
  • Predecessors and relationship type
  • Duration
  • Early start and early finish
  • Late start and late finish
  • Total float and free float
  • Critical or near-critical flag
  • Baseline finish and current forecast finish

Done when

  • Every activity except the start and finish milestones has at least one predecessor and one successor.
  • Each lag and date constraint has a written reason tied to real waiting time or a contract date.
  • The critical path runs without a break from the start milestone to the finish milestone.
  • Every activity shows total float, and any unusually high or negative float is explained.
  • The baseline is approved and saved before work starts, with a set status date for updates.

Measure

At each status date, track the forecast finish against the baseline finish and the float left on critical and near-critical paths. Over the project, compare the share of critical activities that finish on their baseline dates with your own past projects. It worked when slips show up while float remains and the forecast finish stays within the margin you agreed.

Hypothetical example

Fernhill Builders plans a clinic fit-out. Demolition takes 5 days. Electrical rough-in takes 8 days and plumbing rough-in 6, both after demolition. Drywall takes 7 days and needs both rough-ins. Flooring takes 4 days and fixtures 3. The forward pass gives a 27-day finish. Plumbing has 2 days of total float, and every other activity has none, so the critical path is demolition, electrical, drywall, flooring and fixtures. The client needs 25 days. The team crashes electrical with a second electrician, cutting it to 6 days. The finish becomes day 25, and plumbing now has zero float, so both rough-ins sit on the critical path.

Common mistakes

  • Leaving activities without a successor, so their delays never reach the finish date. Tie every activity into the network.
  • Using lags or date constraints to stand in for work such as a client review. Add the review as an activity with an owner.
  • Watching only the zero-float path. Track near-critical paths too, with a float threshold sized to the project's length.
  • Leveling resources by hand with false links or constraints. Use the tool's leveling settings and check every resource afterward.
  • Giving support work a fixed duration as long as the project, so it drives the critical path. Let support activities take their dates from the work they support.

Sources

By company stage

  1. Pre-IdeaNot applicableThere are no dependent activities to schedule.
  2. IdeaNot applicableTasks are few and changing, so a simple list suffices.
  3. Early StartupNot applicableThe team is small and plans change fast, so dependency analysis adds little.
  4. StartupUsefulUseful for launches with many dependencies across teams.
  5. GrowthUsefulUseful for cross-department programs such as regional expansion.
  6. ScaleUsefulUseful for product launches and integrations with long dependency chains.
  7. EnterpriseUsefulUseful for large programs and construction-like projects with fixed finish dates.

Apply first

Nothing. You can start here.

Use instead