Operations · Operations & process management
Earned value management (EVM)
Best for Enterprise
Use it when
You run a project with a baselined schedule and budget, and need monthly cost and schedule variances plus a forecast of the final cost.
Skip it when
- You have no logic-linked schedule with a baseline yet. Build one with Critical path method (CPM) first.
- You are tracking a department's annual budget with no link to the work completed. Use Budget planning & control framework.
- You need to explain why operating results differ from budget in an ongoing business. Use Variance analysis framework.
- You run a small marketing project and need a charter, sign-offs and weekly checks against dates. Use Project management framework.
What to apply first and what to use instead are listed below.
Inputs
- Work breakdown structureOne structure shared by the cost estimate and the schedule, from the project plan.
- Control accountsThe points where each work breakdown element meets the manager responsible for it, from the organization chart.
- Baselined scheduleA logic-linked schedule with its critical path and baseline dates, from the scheduling tool.
- Time-phased budgetBudget per work package per month, summing to the budget at completion, with management reserve held outside the baseline.
- Earned value method per work packageFixed formula, weighted milestone, percent complete or physical measurement, agreed with each control account manager before work starts.
- Actual costsCosts recorded per control account for each monthly period, from the accounting system.
Steps
- Define the scope in one work breakdown structure, assign every element to a control account manager, and schedule the work with logic links.
- Budget each work package by month and set its earned value method before work starts. Keep 0/100 for packages inside one period and 50/50 for packages inside two, and use level of effort sparingly. Sum the budgets into the performance measurement baseline.
- At each month end, record planned value, earned value and actual cost for every control account.
- Calculate cost variance (EV minus AC), schedule variance (EV minus PV), CPI (EV over AC) and SPI (EV over PV), for the month and to date. Sort accounts by variance percent and trace the largest to a root cause.
- Forecast the estimate at completion with more than one formula, such as budget at completion over CPI and the composite of CPI and SPI, and compare them with the team's bottom-up estimate.
- Agree corrective actions with owners, and change the baseline only through approved changes, never inside the current period.
Output
A monthly earned value report by control account with variances, indices and a forecast of the final cost.
- Control account and manager
- Planned value, earned value and actual cost, for the month and to date
- Cost and schedule variance in money and percent
- CPI and SPI
- Estimates at completion by formula and from the team, with variance at completion
- To-complete performance index
- Variance cause and corrective action with owner
Done when
- Every work package has a monthly budget and an earned value method set before its work started.
- Planned value at completion equals the budget at completion, with management reserve outside the baseline.
- Planned value, earned value and actual cost cover the same period for every control account.
- Every account with a CPI or SPI to date below 0.95 has a named cause and action.
- The report shows at least two estimates at completion and the variance at completion.
Measure
Each month, track CPI and SPI to date and the spread between your estimates at completion. At project close, compare the final cost with the estimates you made at each stage, and compare that accuracy with your past projects. It worked when variances triggered action early and your estimates at completion settled near the final cost well before the end.
Hypothetical example
Halvorsen Labs is three months into a 1.2 million dollar lab rebuild. Planned value to date is 400,000 dollars, earned value is 340,000 and actual cost is 380,000. Cost variance is minus 40,000 and schedule variance is minus 60,000. CPI is about 0.89 and SPI 0.85, both under the 0.95 warning line. Budget at completion over CPI gives an estimate near 1.34 million, a variance at completion of about minus 140,000. Sorting accounts shows ventilation drives most of the gap, because a late duct supplier caused rework. The manager adds a second supplier, and the team records the new forecast with the sponsor.
Common mistakes
- Claiming progress by guessing a percent complete. Set objective measures such as milestones passed or units installed before work starts.
- Booking large parts of the budget as level of effort, which earns value just as time passes. Review it once it passes 15 percent of the budget.
- Reading only the project total, where one weak account hides behind a strong one. Analyze each work breakdown element.
- Moving planned value into later months to improve this month's figures. Freeze the current period and change the baseline only through approved changes.
- Relying on one forecast formula. Compare CPI-based and composite estimates with the team's own estimate of the remaining work.
Sources
- Cost Estimating and Assessment Guide: Best Practices for Developing and Managing Program Costs (GAO-20-195G) · US Government Accountability Office, 2020
- Earned Value Management System (EVMS) Gold Card · US Department of Energy, Office of Project Management, 2019
- Earned Value Management System (EVMS) and Project Analysis Standard Operating Procedure (EPASOP), DOE-PM-SOP-05-2020 · US Department of Energy, Office of Project Management, 2020
Show all 4 sources
- EVMS Implementation Guidance · US Department of Energy, Office of Project Management, 2024
By company stage
Apply first
- Critical path method (CPM)Operations · Operations & process management
Earned value is measured against a scheduled baseline, which the critical path method builds.
Use instead
- Critical path method (CPM)
You have no logic-linked schedule with a baseline yet. Build one with Critical path method (CPM) first.
- Budget planning & control framework
You are tracking a department's annual budget with no link to the work completed. Use Budget planning & control framework.
- Variance analysis framework
You need to explain why operating results differ from budget in an ongoing business. Use Variance analysis framework.
- Project management framework
You run a small marketing project and need a charter, sign-offs and weekly checks against dates. Use Project management framework.
Where it sits
Open the operations & process management roadmapRecommended resources
No sponsored resources on this framework yet. Sponsored listings would be labelled here, never in search.
Progress is not saved until you have an account. Create a free account